Two senior developers on an agile team openly disagree about the technical approach for a critical feature, and the tension is starting to affect daily standups. As the project manager applying a servant-leadership mindset, what should you do first?
Correct: B. The most effective conflict-resolution mode is collaborate/problem-solve, which addresses root causes and preserves the relationship. Escalating (B-style avoidance) removes the team's ownership and is a common trap; deciding for them (forcing) damages buy-in; reassigning avoids the real issue.
A project manager notices a normally vocal team member has gone quiet and is missing commitments after a personal setback. What demonstrates the strongest emotional intelligence?
Correct: B. Self-awareness and empathy (core EI components) call for a private, supportive conversation. Documenting first (B) is the punitive trap; a public reminder shames the person; waiting passively ignores a visible signal a leader should act on.
During Scrum sprint planning, the team consistently over-commits and fails to finish the sprint backlog. As the team's coach, what is the best long-term action?
Correct: B. Self-organizing teams improve by inspecting empirical velocity and right-sizing their commitment (empiricism + self-management). Mandating overtime (B) burns the team out and hides the real problem; lengthening the sprint reduces feedback frequency; pre-assigning work breaks self-organization.
A key stakeholder keeps bypassing the project manager and giving conflicting direction directly to team members. What is the most appropriate first response?
Correct: B. Stakeholder engagement starts with direct, respectful dialogue to set expectations and protect the team. Telling the team to ignore them (B) creates an adversarial split; jumping to the sponsor skips the lowest-effective-escalation step; logging change requests does not fix the relationship problem.
You are forming a new virtual team spread across three time zones. To build trust and shared understanding early, which actions should you take? (Choose 2)
Correct: B and D. Distributed teams need co-created ground rules and fair overlap windows to build trust. A read-it-yourself charter skips the relational kickoff; email-only kills synchronous bonding; imposing one zone's hours breeds resentment and ignores fairness.
Last updated:
Yes. You can start, finish and score it for free, and download the Techclick practice certificate.
This bank has 60 original scenario-based questions with a 120-minute timer and a 61% Techclick practice target.
The official exam code is PMP (PMI).
No. They are original practice questions written by Techclick. This is not the vendor's official exam and not leaked dumps.
Score 61% or higher to get a Techclick practice certificate and LinkedIn badge. It is not an official PMI certification.
Use the PMI practice exams page (linked above) to pick the next practice test in the same track.

You earned it — let the world know!