A stakeholder asks why Scrum insists on short Sprints and frequent inspection instead of one detailed up-front plan. What is the best explanation?
Correct: A. Scrum is grounded in empiricism (transparency, inspection, adaptation) and lean thinking. The trap (B) frames Sprints as fixed-scope contracts — Scrum optimizes value, not adherence to an original plan. (C) misuses inspection for surveillance; (D) contradicts empiricism, which exists precisely because the future cannot be fully predicted.
Which of the following are the three pillars that uphold every implementation of empirical process control in Scrum? (Choose 3)
Correct: A and B and C. The three empirical pillars are Transparency, Inspection, and Adaptation. "Commitment" is a Scrum Value (not a pillar); "Estimation" and "Velocity" are practices/metrics, not pillars. Mixing values, metrics, and pillars is the classic trap here.
According to the 2020 Scrum Guide, what are the five Scrum Values? (Choose 3 of the values listed below.)
Correct: A and B and C. The five Scrum Values are Commitment, Focus, Openness, Respect, and Courage. Of the options shown, Commitment, Focus, and Openness are real values. "Predictability", "Efficiency", and "Accountability" are common-sounding distractors that are NOT Scrum Values.
Inspection in Scrum is only useful when which condition is met first?
Correct: A. The Scrum Guide states inspection enables adaptation, but inspection without transparency is misleading and wasteful. (B), (C), and (D) invent gating conditions that do not exist; inspection happens continuously throughout the Sprint.
A new Scrum Master notices the team treats Scrum as a fixed set of steps to obey. How should empiricism be framed instead?
Correct: A. The Scrum Guide explicitly calls Scrum lightweight and purposefully incomplete. (B) wrongly calls it a complete methodology; (C) makes the Scrum Master a process dictator (Scrum Teams are self-managing); (D) is nonsensical — the PO is a core accountability.
Last updated:
Yes. You can start, finish and score it for free, and download the Techclick practice certificate.
This bank has 60 original scenario-based questions with a 60-minute timer and a 85% Techclick practice target.
The official exam code is PSM I (Scrum.org).
No. They are original practice questions written by Techclick. This is not the vendor's official exam and not leaked dumps.
Score 85% or higher to get a Techclick practice certificate and LinkedIn badge. It is not an official Scrum.org certification.
Use the Scrum.org practice exams page (linked above) to pick the next practice test in the same track.

You earned it — let the world know!